Weekly Progress Report - 31.08.2020 to 05.09.2020 |
31.08.2020 |
01.09.2020 |
02.09.2020 |
03.09.2020 |
04.09.2020 |
05.09.2020 |
No work at site |
Reinforcement installation for Retaining Wall (at Grid F) |
Reinforcement installation for Retaining Wall (at Grid F) |
Reinforcement installation for Retaining Wall (at Grid F) & Lift Shaft Wall in Academic Building |
Reinforcement tying for Retaining Wall (at Grid F) & Lift Wall in Academic Building |
Shuttering work for stairs and columns at Zone A. |
|
Solid Blockwork & Plastering works for Plinth walls in Engineering Block |
Lift Shaft Wall in Academic Building |
Form-work preparation/installation for the remaining part of slab at -2.70m level at Zone A in Academic Building
|
Shuttering work for stairs at Zone A in Academic Building
|
Form-work preparation/installation for slab at -2.70m level at Zone A.
|
|
|
Cutting and bending of reinforcement for the slab,beams and columns. |
Cutting and bending of reinforcement for the slab,beams and columns.
|
Form-work preparation/installation for slab at -2.70m level at Zone A in Academic Building
|
Soil Backfilling inside Plinth at Zone B
|
|
|
|
Solid Blockwork & Plastering works for Plinth walls in Engineering Block |
Soil Backfilling inside Plinth at Zone B in Academic Building
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
|
|
|
|
Solid Blockwork & Plastering works for Plinth walls in Engineering Block |
Solid Blockwork & Plastering works for Plinth walls in Engineering Block |