   Weekly report as on 04.03.2011
    

 

Progress Report For Mulamkunnathukavu ROB for the week ending on 04-03-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 9 0 0 0 0 0 0  
2 PILE M.C SIDE 36 36 0 0 0 0 0 0  
3 PILE CAP SHORNUR SIDE 3 3 0 0 0 0 0 0  
4 PILE CAP  M.C SIDE 12 12 0 0 0 0 0 0  
5 PIER SHORNUR  SIDE 3 3 0 0 0 0 0 0  
6 PIER M.C SIDE 12 12 0 0 0 0 0 0  
7 PIER CAP SHORNUR  SIDE 3 3 0 0 0 0 0 0* pedestal concreting
8 PIER CAP M.C SIDE 12 12 0 0 0 0 0 0 pedestal concreting completed 5 locations.P13,P12,P11,P10,P9
9 RE/R WALL SHORNUR  SIDE 100% 0 96% 0 10.00% 11.00% 0.00% 15.00% earthwork excavation 
10 RE/R WALL M.C SIDE 100% 1% 99% 0 5.00% 5.00% 0.00% 10.00% casting of panels 120no: completed.
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0*  
12 BEAM/SLAB M.C SIDE 12 0 12 0 1 0 1 2 reinforcement and shuttering works of beam and deck slab for span P11-P12 is  completed. progress.concreting to be done tomorrow {4-3-2011
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

Availbility of Men             
Date 26-2-'11 27-2-'11 28-2-'11 1/3/2011   2-3-2-'11 3/3/2011
Nof labours 42 42 42 42   42 42 

 

Material Stocking Status        
  Required Available Remarks      
Fine aggregate {m³} 60 75        
Cement(bag) 700 500 stock wiill be replenished before next Monday   today evening {3-3-2011  
Steel inT 12.35 21 sufficient material available at the site      
Coarse Aggreagate (m3) 80 200        

 

Utility shifting        
Utilities to be shifted   Remarks    
BSNL no hindrance      
KSEB already shifted      
KWA no hindrance      
Others road diversion work{earthwork excavation }for sectioning}started  today started next week     
  no hindrance from marble shop         
 