Weekly Progress Report - 31.08.2020 to 05.09.2020 |
31.08.2020 |
01.09.2020 |
02.09.2020 |
03.09.2020 |
04.09.2020 |
05.09.2020 |
No work at site |
No work at site |
Shuttering works for girder between P2-P3 in progress. |
Kuttipuram side
Concrete for Girder at P7-A2 |
Shuttering works for Girder at P2-P3 |
Shuttering works for Girder at P2-P3 |
|
|
Reinforcement works at yard for Girder . |
Thrissur side.
Shuttering works for Girder at P2-P3 |
Reinforcement works for Girder . |
Deshuttering for shuttering of girder at P7- A2 |
|
|
|
|
|
Reinforcement works for Girder . |
|
|
|
|
|
|
|
|
|
|
|
|