Weekly Progress Report - 31.08.2020 to 05.09.2020 |
31.08.2020 |
01.09.2020 |
02.09.2020 |
03.09.2020 |
04.09.2020 |
05.09.2020 |
No work at site |
No major works at site |
Cleaning work in embankment area for DBM work at Aroor side (Crown plaza side). |
Putty work on crash barrier outside side (Le meridian side). |
DBM work at aroor side (Crown plaza side) |
Putty work on crash barrier outside side (Le meridian side). |
|
|
Putty work on crash barrier outside at Aroor side (Le meridian side). |
Cleaning work in embankment area for DBM work at Aroor side (Crown plaza side). |
Shuttering work completed. Ready for concrete for drain near pamba steel. |
Drain wall concreting - 12m |
|
|
Reinforcement work for drain near pamba steel. |
Shuttering work for drain near pamba steel. |
Metal beam crash barrier work progressing at aroor side (Crown plaza side) |
Reinforcement work for drain raft near pamba steel. |
|
|
|
Levelling work for under passage (P12-P13) |
Putty work on crash barrier outside side (Le meridian side). |
Metal beam crash barrier work progressing at aroor side (Crown plaza side) |
|
|
|
Metal beam crash barrier work progressing at aroor side (Crown plaza side). and PCC work. |
Levelling work for under passage (P12-P13) |
|