   Weekly Progress Report - 24.08.2020 to 29.08.2020
    
Weekly Progress Report - 24.08.2020 to 29.08.2020
24.08.2020 25.08.2020 26.08.2020 27.08.2020 28.08.2020 29.08.2020
Grill fabrication work for windows. Granite laying at fire stair. Aluminum fabrication works Aluminum fabrication works Granite flooring at fire stair. Granite flooring at fire stair.
Aluminum fabrication works. Aluminum fabrication works Grill fabrication work.
Grill fabrication work.
Aluminum works.
Aluminum works.
Electrical work at 6th floor. Grill fabrication work.    
Grill fabrication work.
Grill fabrication work.
Granite shifting.
     
Plumbing works.
 
           
 
Back
 
    
ALUMINUM WINDOW WORK

    
    
GRANITE WORK

    
    
PLUMBING WORK

    
    
WINDOW GRILL FABRICATION WORK

    
 
    
WINDOW GRILL FABRICATION WORK

    
    
ALUMINUM FABRICATION WORK

    
    
GRILL FABRICATION WORK

    
 
    
ALUMINUM WORK

    
    
GRILL FABRICATION WORK

    
    
GRANITE WORK

    
 
    
ALUMINUM FABRICATION WORK

    
    
GRILL FABRICATION WORK

    
    
ELECTRICAL WORK

    
 
    
ALUMINUM FABRICATION WORK

      
 

 

 

 

 

 

 

 