   Weekly Progress Report - 24.08.2020 to 29.08.2020
    
Weekly Progress Report - 24.08.2020 to 29.08.2020
24.08.2020 25.08.2020 26.08.2020 27.08.2020 28.08.2020 29.08.2020
 Levelling work starts in embankment area (Aroor side). Compaction work  in embankment area (Aroor side). Compaction work  in embankment area (Aroor side).
 
Compaction work in embankment area at Aroor side (Crown plaza side). Compaction work  in embankment area at Aroor side (Crown plaza side). Compaction work  in embankment area at Aroor side (Crown plaza side).
Painting work  on P12 & P7 pier cap.  Putty work  on P11 pier cap.
Putty work  on P12-P13 span and crash barrier outside (Aroor side) .
 


Putty work  on crash barrier outside at Aroor side (Le meridian side).
 
Putty work  on crash barrier outside at Aroor side (Le meridian side). Putty work  on crash barrier outside at Aroor side (Le meridian side)
Metal beam crash barrier work progressing at aroor side (Le meridian side) Metal beam crash barrier work progressing at aroor side (Le meridian side) Metal beam crash barrier work progressing at aroor side (Le meridian side)
 

Metal beam crash barrier work progressing at aroor side (Le meridian side)
 
Metal beam crash barrier work progressing at aroor side (Crown plaza side)  Deshuttering work at drain wall near pamba steel.
Compaction work at A2 side (Crown plaza side) for road widening.
 
Deshuttering and Shuttering work at drain wall near pamba steel.
Shuttering work (10m) at drain wall completed planning for concreting.

Deshuttering and Shuttering work at drain wall near pamba steel.
 
Shuttering work at drain wall completed and concrete done. Planning for PCC work for drain near pamba steel.
Shuttering work at drain wall completed and concrete done Cleaning work starts at A1 approach side (Crown plaza side) for doing applying prime coat.
Kerb stone fixing work starts at A1 approach side Median area.

DBM work at A1 approach side (Le meridian side).
Planning for DBM work at A2 approach side (Le meridian side) and A1 approach side (Crown plaza side) (Rectificatied area) Hand rail work progressing on A1 vyttila side (Le meridian side).
 
Back
 
    
DE SHUTTERING WORK

    
    
HANDRAIL WORK

    
    
PUTTY WORK

    
    
COMPACTION WORK

    
 
    
DRAIN CONCRETE WORK

    
    
COMPACTION WORK

    
    
PUTTY WORK

    
 
    
PRIME COAT WORK FOR DBM

    
    
SHUTTERING WORK FOR DRAIN

    
    
COMPACTION WORK

    
 
    
CLEANING WORK FOR APPLYING PRIME COAT

    
    
METAL CRASH BARRIER WORK

    
    
DBM WORK

    
 
    
PRIME COAT WORK FOR DBM

    
    
PUTTY WORK

    
    
DE SHUTTERING WORK

    
 
    
KERB STONE FIXING

    
    
KERB STONE FIXING

    
    
COMPACTION WORK

    
 
    
SHUTTERING WORK FOR DRAIN

    
    
DRAINAGE WORK FOR BRIDGE SPAN

    
    
PUTTY WORK

    
 
    
METAL CRASH BARRIER WORK

    
    
PUTTY WORK

    
    
COMPACTION WORK

    
 
    
KERB STONE FIXING

    
    
CLEANING WORK FOR APPLYING PRIME COAT

    
    
METAL CRASH BARRIER WORK

    
 
    
PUTTY WORK

    
    
DE SHUTTERING WORK

    
    
DRAIN CONCRETE WORK

    
 
    
PAINTING WORK

    
    
LEVELLING WORK

    
    
COMPACTION WORK

    
 
    
METAL CRASH BARRIER WORK

      
 

 

 

 

 

 

 

 