Weekly Progress Report - 24.08.2020 to 29.08.2020 |
24.08.2020 |
25.08.2020 |
26.08.2020 |
27.08.2020 |
28.08.2020 |
29.08.2020 |
Levelling work starts in embankment area (Aroor side). |
Compaction work in embankment area (Aroor side). |
Compaction work in embankment area (Aroor side).
|
Compaction work in embankment area at Aroor side (Crown plaza side). |
Compaction work in embankment area at Aroor side (Crown plaza side). |
Compaction work in embankment area at Aroor side (Crown plaza side). |
Painting work on P12 & P7 pier cap. |
Putty work on P11 pier cap. |
Putty work on P12-P13 span and crash barrier outside (Aroor side) .
|
Putty work on crash barrier outside at Aroor side (Le meridian side).
|
Putty work on crash barrier outside at Aroor side (Le meridian side). |
Putty work on crash barrier outside at Aroor side (Le meridian side) |
Metal beam crash barrier work progressing at aroor side (Le meridian side) |
Metal beam crash barrier work progressing at aroor side (Le meridian side) |
Metal beam crash barrier work progressing at aroor side (Le meridian side)
|
Metal beam crash barrier work progressing at aroor side (Le meridian side)
|
Metal beam crash barrier work progressing at aroor side (Crown plaza side) |
Deshuttering work at drain wall near pamba steel. |
Compaction work at A2 side (Crown plaza side) for road widening.
|
Deshuttering and Shuttering work at drain wall near pamba steel. |
Shuttering work (10m) at drain wall completed planning for concreting. |
Deshuttering and Shuttering work at drain wall near pamba steel.
|
Shuttering work at drain wall completed and concrete done. |
Planning for PCC work for drain near pamba steel. |
Shuttering work at drain wall completed and concrete done |
Cleaning work starts at A1 approach side (Crown plaza side) for doing applying prime coat. |
Kerb stone fixing work starts at A1 approach side Median area. |
DBM work at A1 approach side (Le meridian side). |
Planning for DBM work at A2 approach side (Le meridian side) and A1 approach side (Crown plaza side) (Rectificatied area) |
Hand rail work progressing on A1 vyttila side (Le meridian side). |