Weekly Progress Report - 24.08.2020 to 29.08.2020 |
24.08.2020 |
25.08.2020 |
26.08.2020 |
27.08.2020 |
28.08.2020 |
29.08.2020 |
Deshuttering works in progress for 3rd girder at A1-P1. |
Reinforcement work for girder-1 between P2-P3 |
Reinforcement work for girder-1 between P2-P3 |
Reinforcement work for girder-1 between P2-P3 |
Reinforcement works and cable profiling for girder at P2-P3 at Thrissur side. |
Reinforcement works and cable profiling for girder at P2-P3 |
Arranging reinforcement for girder works atP2-P3. |
Shuttering work for girder-2 between A2-P7 |
Shuttering work for girder-2 between A2-P7 |
Reinforcement work for girder-3 between A2-P7 |
Kuttipuram side
Reinforcement works for girder for P7-A2 |
Reinforcement works for girder for P7-A2 |
Kuttipuram side.
Shuttering works for second girder at P7-A2. |
Reinforcement work for girder-3 between A2-P7 |
Reinforcement work for girder-3 between A2-P7 |
PCC bed work for girder between P2-P3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|