Weekly Progress Report - 17.08.2020 to 22.08.2020 |
17.08.2020 |
18.08.2020 |
19.08.2020 |
20.08.2020 |
21.08.2020 |
22.08.2020 |
Brick work for Plinth walls at Zone B in Academic Block |
Brick work for Plinth walls at Zone B in Academic Block |
Brick work for Plinth walls at Zone B in Academic Block |
Plastering work for Plinth walls at Zone B. |
Block work construction & Plastering work for Plinth walls at Zone B. |
Block work construction & Plastering work for Plinth walls at Zone B. |
Reinforcement tying for lift wall at Zone A, Retaining wall at Grid F. |
Reinforcement tying for lift wall at Zone A, Retaining wall at Grid F.
|
Reinforcement tying for lift wall at Zone A, |
Shuttering work for Retaining walls at Grid F.
|
Shuttering work for Lift wall & Retaining walls at Grid F. |
Shuttering work for Lift wall & Retaining walls at Grid F. |
Cutting and bending of reinforcement for the slab,beams and columns. |
Cutting and bending of reinforcement for the slab,beams and columns. |
Shuttering work for Retaining walls at Grid F. |
Reinforcement tying for column at zone A.
|
Reinforcement tying for column at zone A. |
Reinforcement tying for column at zone A |
Shuttering work for stairs in Engineering Dept. Block |
Shuttering work for stairs in Engineering Dept. Block |
Cutting and bending of reinforcement for the slab,beams and columns. |
Cutting and bending of reinforcement for the slab,beams and columns. |
Cutting and bending of reinforcement for the slab,beams and columns. |
Cutting and bending of reinforcement for the slab,beams and columns |
|
Shuttering work for columns in International Guest House Block |
Shuttering work for columns in International Guest House Block |
Shuttering work for columns in International Guest House Block |
|
|