Weekly Progress Report - 17.08.2020 to 22.08.2020 |
17.08.2020 |
18.08.2020 |
19.08.2020 |
20.08.2020 |
21.08.2020 |
22.08.2020 |
Plumbing work at 1st floor duct
|
Electrical work at 1st floor
|
Aluminum fabrication work. |
Granite flooring at main stair |
Aluminum work at 7th floor. |
Aluminum work at 7th floor. |
Aluminum work started at site.
|
Plumbing work at 2nd floor gents toilet
|
Pumbing work at duct. |
Elevator work at lift L3 work.
|
Electrical work at 2nd floor.
|
Electrical work at 2nd floor. |
Call button installation at lift L1
|
Aluminum fabrication work.
|
Granite flooring at main stair. |
Aluminum fabrication work
|
Plumbing work at 5th floor gents toilet
|
Plumbing work at 5th floor gents toilet |
|
Lift L3 machine room works.
|
Elevator work at lift L1. |
Plumbing work at gents toilet.
|
Tile flooring at 1st floor.
|
|
|
|
Electrical work at 1st floor.
|
|
|
|