   Weekly Progress Report - 17.08.2020 to 22.08.2020
    
Weekly Progress Report - 17.08.2020 to 22.08.2020
17.08.2020 18.08.2020 19.08.2020 20.08.2020 21.08.2020 22.08.2020
Plumbing work at 1st floor duct
Electrical work at 1st floor
Aluminum fabrication work. Granite flooring at main stair Aluminum work at 7th floor. Aluminum work at 7th floor.
Aluminum work started at site.
Plumbing work at 2nd floor gents toilet
Pumbing work at duct.
Elevator work at lift L3 work.
Electrical work at 2nd floor.
Electrical work at 2nd floor.
Call button installation at lift L1
 
Aluminum fabrication work.
Granite flooring at main stair.
Aluminum fabrication work
Plumbing work at 5th floor gents toilet
Plumbing work at 5th floor gents toilet
 
Lift L3 machine room works. 
Elevator work at lift L1.
Plumbing work at gents toilet.
Tile flooring at 1st floor.
 
   
Electrical work at 1st floor.
     
 
Back
 
    
TILE WORK

    
    
PLUMBING WORK

    
    
ELECTRICAL WORK

    
    
ALUMINUM FABRICATION WORK

    
 
    
GRANITE WORK

    
    
ELEVATOR WORK

    
    
ALUMINUM FABRICATION WORK

    
 
    
PLUMBING WORK

    
    
PLUMBING WORK

    
    
ELEVATOR WORK

    
 
    
ELECTRICAL WORK

    
    
GRANITE WORK

    
    
ALUMINUM WORK

    
 
    
LIFT MACHINE ROOM WORK

    
    
ALUMINIUM WORK

    
    
PLUMBING WORK

    
 
    
ELECTRICAL WORK

    
    
PLUMBING WORK

    
    
ALUMINIUM WORK

    
 
    
CALL BUTTON INSTALLATION

      
 

 

 

 

 

 

 

 