Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886508
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report - 17.08.2020 to 22.08.2020
    
Weekly Progress Report - 17.08.2020 to 22.08.2020
17.08.2020 18.08.2020 19.08.2020 20.08.2020 21.08.2020 22.08.2020
Painting work progressing at P7-P8 span and P10 pier cap WMM filling at Aroor side embankment area WMM filling and compaction progressing at embankment area (Aroor side).
 
Putty work progressing at Outside crash barrier at Aroor side. WMM laying at  Aroor side embankment DBM work at A1 approach side (Vyttila side LHS)
Putty work at crash barrier (outside area) at Aroor side Putty work progressing at P8-P9 span  Putty work progressing at P9-P10 span, Outside crash barrier at Aroor side and Painting at P10 pier cap.
 
Painting work progressing at P10 pier cap side. Drain wall shuttering work and excavation for drain near pampa steel Primer coating and putty work  on P11- P12  span.
GSB filling work for road widening at aroor side (Le meridian side) Painting at P10, P12 pier cap Metal beam crash barrier work at aroor side (Le meridian side)
 
Primer coating work on P8-P9 & P9-P10 span. Painting work Metal beam crash barrier work progressing at aroor side (Le meridian side)
 
Reinforcement work for cast - in-situ drainage at Pamba steel area (Vyttila side). Site clearing work and excavation  at Thripunitura road for drainage Drain excavation at thripunitura road and Shuttering work for drain wall at pamba steel area.
 
 Metal beam crash barrier work progressing at aroor side (Le meridian side) Metal beam crash barrier work at Aroor side Compaction work at embankment area (Aroor side).
Placing of precast drain (for 15m) and excavation for drain is progressing Deshuttering work at A2 Median side Drainage spout fixing work starts. Applying prime coat at A1 approach side. Prime coat work Wall Shuttering (12m) for drain completed. They are planning for doing concreting.
 
Back
 
    
DBM WORK

    
    
DBM WORK

    
    
DBM WORK

    
    
METAL CRASH BARRIER WORK

    
 
    
SHUTTERING WORK FOR DRAIN

    
    
PUTTY WORK

    
    
METAL CRASH BARRIER WORK

    
 
    
SHUTTERING WORK FOR DRAIN

    
    
EXCAVATION FOR DRAIN

    
    
PRIME COAT WORK FOR DBM

    
 
    
COMPACTION WORK

    
    
PAINTING WORK

    
    
PRIME COAT WORK FOR DBM

    
 
    
METAL CRASH BARRIER WORK

    
    
PAINTING WORK

    
    
PUTTY WORK

    
 
    
PUTTY WORK

    
    
PUTTY WORK

    
    
PAINTING WORK

    
 
    
COMPACTION WORK

    
    
PUTTY WORK

    
    
METAL CRASH BARRIER WORK

    
 
    
WMM FILLING

    
    
DESHUTTERING WORKS

    
    
PAINTING WORK

    
 
    
PAINTING WORK

    
    
PUTTY WORKS

    
    
SITE CLEARING

    
 
    
APPROACH WIDENING WORK

    
    
PAINTING WORK

    
    
PUTTY WORKS

    
 
    
PAINTING WORK

    
    
DRAINAGE WORK

    
    
REINFORCEMENT WORK

    
 
 
 

 

 

 

 

 

 

 

Untitled Document