Weekly Progress Report - 17.08.2020 to 22.08.2020 |
17.08.2020 |
18.08.2020 |
19.08.2020 |
20.08.2020 |
21.08.2020 |
22.08.2020 |
Painting work progressing at P7-P8 span and P10 pier cap |
WMM filling at Aroor side embankment area |
WMM filling and compaction progressing at embankment area (Aroor side).
|
Putty work progressing at Outside crash barrier at Aroor side. |
WMM laying at Aroor side embankment |
DBM work at A1 approach side (Vyttila side LHS) |
Putty work at crash barrier (outside area) at Aroor side |
Putty work progressing at P8-P9 span |
Putty work progressing at P9-P10 span, Outside crash barrier at Aroor side and Painting at P10 pier cap.
|
Painting work progressing at P10 pier cap side. |
Drain wall shuttering work and excavation for drain near pampa steel |
Primer coating and putty work on P11- P12 span. |
GSB filling work for road widening at aroor side (Le meridian side) |
Painting at P10, P12 pier cap |
Metal beam crash barrier work at aroor side (Le meridian side)
|
Primer coating work on P8-P9 & P9-P10 span. |
Painting work |
Metal beam crash barrier work progressing at aroor side (Le meridian side)
|
Reinforcement work for cast - in-situ drainage at Pamba steel area (Vyttila side). |
Site clearing work and excavation at Thripunitura road for drainage |
Drain excavation at thripunitura road and Shuttering work for drain wall at pamba steel area.
|
Metal beam crash barrier work progressing at aroor side (Le meridian side) |
Metal beam crash barrier work at Aroor side |
Compaction work at embankment area (Aroor side). |
Placing of precast drain (for 15m) and excavation for drain is progressing |
Deshuttering work at A2 Median side |
Drainage spout fixing work starts. |
Applying prime coat at A1 approach side. |
Prime coat work |
Wall Shuttering (12m) for drain completed. They are planning for doing concreting. |