Weekly Progress Report - 17.08.2020 to 22.08.2020 |
17.08.2020 |
18.08.2020 |
19.08.2020 |
20.08.2020 |
21.08.2020 |
22.08.2020 |
Concrete of girder-1 between P6 -P7 |
Deshuttering work of girder-1 between P7- A2 |
Profile work for girder-2 between P7- A2 |
Profile work for girder- 2 between A2-P7 |
Reinforcement and profile work for girder-2 between A2-P7 |
Girder -3 concrete between A1- P1 |
Profilework for girder -2 between P6-P7 |
Profile work for girder-2 between P7- A2 |
Deshuttering work of girder-1 between P7- A2 |
Reinforcement work for girder-3 between P7-A2 |
Reinforcement work for girder -3 between A2-P7 |
Shuttering work of girder-2 between A2-P7 |
Shuttering work for girder- 3 between A1-P1 |
Reinforcement work for girder -3 between P7-A2 |
Reinforcement work for girder -3 between P7-A2 |
Shuttering work for girder -3 between A1-P1 |
PCC bed work for girders between P2- P3 |
Reinforcement work for girder-3 between A2-P7 |
|
Shuttering work for girder -3 between A1-P1 |
Shuttering work for girder -3 between A1-P1 |
|
|
|
|
|
PCC bed work for girder casting between P2 - P3 |
|
|
|