   Weekly Progress Report - 10.08.2020 to 15.08.2020
    
Weekly Progress Report - 10.08.2020 to 15.08.2020
10.08.2020 11.08.2020 12.08.2020 13.08.2020 14.08.2020 15.08.2020
Elevator work at lift L2.
Elevator work at lift L2.
Plumbing work at duct. Elevator work at lift L1
Plumbing work at 1st floor duct
Plumbing work at 1st floor duct
Tile flooring at 2nd floor. Electrical work at 2nd floor.
Elevator work at lift L2.
Electrical work at 1st floor.
Tile flooring at 2nd floor.
Granite flooring at main stair.
   
Electrical work at 2nd floor.
Granite flooring at main stair.
Electrical work at 1st floor
 
     
Plumbing work at duct
   
           
 
Back
 
    
PLUMBING WORK

    
    
GRANITE WORK

    
    
ELEVATOR WORK

    
    
PLUMBING WORK

    
 
    
TILE WORK

    
    
PLUMBING WORK

    
    
ELEVATOR WORK

    
 
    
GRANITE WORK

    
    
ELECTRICAL WORK

    
    
PLUMBING WORK

    
 
    
ELECTRICAL WORK

    
    
ELECTRICAL WORK

    
    
ELEVATOR WORK

    
 
    
TILE WORK

      
 

 

 

 

 

 

 

 