Weekly Progress Report - 10.08.2020 to 15.08.2020 |
10.08.2020 |
11.08.2020 |
12.08.2020 |
13.08.2020 |
14.08.2020 |
15.08.2020 |
Reinforcement works for Girder at first span..(6th beam) on Thrissur side
|
Reinforcement work for girder-3 between A1-P1
|
Reinforcement work for girder-2 between P6-P7
|
Shuttering work for girder-1 between P6-P7
|
Shuttering work for girder-1 between P6 -P7 ( concrete planning on monday)
|
No work at site |
Reinforcement works for second beam on kuttippuram side
|
Reinforcement work for girder-2 between P6-P7
|
Shuttering work for girder-1 between P6-P7
|
Reinforcement work and profile work for girder-3 between A1-P1
|
Reinforcement work and profile work for girder -3 between A1-P1
|
|
Shuttering works for first beam on kuttippuram side
|
Shuttering work for girder-1 between P6-P7
|
Bottem shutter work for girder-3 between P6-P7
|
Profile work for girder- 2 between P6-P7 |
Site clearance work for pcc bed work to cast girder between P2 -P3
|
|
|
PCC bed work for girder-3 between P6-P7
|
Reinforcement work for girder-3 between A1-P1 |
|
|
|
|
|
|
|
|
|