Weekly Progress Report - 10.08.2020 to 15.08.2020 |
10.08.2020 |
11.08.2020 |
12.08.2020 |
13.08.2020 |
14.08.2020 |
15.08.2020 |
Compaction work (Plain rolling) in embankment area (Arror side) |
Putty work at crash barrier (outside area) |
GSB filling aroor side - 10 load. |
GSB Compaction work in embankment area (Arror side) |
Painting work at P11-P12. |
No work at site |
Putty work at crash barrier (outside area) |
Metal crash barrier work progressing at Aroor side |
Drain erection - 10 nos |
Putty work at crash barrier (outside area) |
Putty work at crash barrier (outside area) at Vyttila side, P7-P8 span |
|
Metal crash barrier work progressing at Aroor side |
Excavation work at Thripunitura road drain portion. |
Metal beam crash barrier supporting PCC - 2 cum |
Kerb stone fixing work at P9, P10 locations. |
Reinforcement work (steel bending for drain at pamba steel area.) |
|
Excavation work at Thripunitura road drain portion. |
Painting work Progressing at Pier, pier cap on P9 location. |
Painting First coat - 1 pier cap and Putty work at crash barrier (outside area) |
Reinforcement work progressing at A2 side Median portion. |
|
|
|
PCC for Kerb stone fixing |
Drainage spout and kerb stone fixing - |
Placing of precast drain for 20m completed. Excavation and PCC for the balance portion is progressing. |
|
|