Weekly Progress Report - 03.08.2020 to 08.08.2020 |
03.08.2020 |
04.08.2020 |
05.08.2020 |
06.08.2020 |
07.08.2020 |
08.08.2020 |
Form-work preparation/installation for slab at -2.70m level, Zone A.
|
Form-work preparation/installation for slab at -2.70m level, Zone A.
|
Form-work preparation/installation for slab at -2.70m level, Zone A. |
Finalising the missing reinforcements installation for beams and slab at -2.70m level, Zone A.
|
No work due to heavy rain. |
Curing of the slab at -2.70m level, Zone A cast on 6th August.
|
Reinforcement installation for beams and slab at -2.70m level, Zone A.
|
Reinforcement installation for beams and slab at -2.70m level, Zone A. |
Reinforcement installation for beams and slab at -2.70m level, Zone A. |
Concrete casting of the slab at -2.70 m level, zone A from Axis A to F/ 6-11
|
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
Electrical conduits laying at -2.70m level, Zone A
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
Cutting and bending of reinforcement for the slab,beams and columns. |
Cutting and bending of reinforcement for the slab,beams and columns.
|
|
Block work construction for Plinth walls at Zone B
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
Block work construction for Plinth walls at Zone B
|
Block work construction for Plinth walls at Zone B |
Shuttering works for the remaining portion of slab at -2.70 m , Zone A.
|
|
Plastering work for Plinth walls at Zone B
|
Block work construction for Plinth walls at Zone B. |
Plastering work for Plinth walls at Zone B
|
Plastering work for Plinth walls at Zone B |
|
|
No work from 1.30 Am due to rain |