Prevoius Weekly Reports

   25.02.2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress uptolast week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

 

Work  Planned for next week

Remarks

1

PILE CALICUT  SIDE

30

30

0

0

0

0

0

0

 

2

PILE NH SIDE

33

33

0

0

0

0

0

0

 

3

PILE RAILWAY SPAN

20

0

20

10

0

0

10

2

 

4

PILE CAP CALICUT  SIDE

10

10

0

0

0

0

0

0

 

5

PILE CAP NH SIDE

11

11

0

0

0

0

0

0

 

6

PILE CAP RAILWAY SPAN

4

0

4

0

0

0

0

1

 

7

PIER CALICUT  SIDE

10

8

2

6

4

2

0

0

 

8

PIER NH SIDE

11

11

0

0

0

0

0

0

 

9

PIER RAILWAY SPAN

4

0

4

0

0

0

0

0

 

10

PIER CAP CALICUT  SIDE

10

0

10

4

3

1

5

3

 

11

PIER CAP NH SIDE

11

4

7

7

4

0

7

4

 

12

PIER CAP RAILWAY SPAN

4

0

4

0

0

0

0

0

 

13

RE/R WALL CALICUT  SIDE

100%

0

100%

0

0.00%

0.01%

0.00%

0.00%

 

14

RE/R WALL NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

15

BEAM/SLAB CALICUT  SIDE

10

0

10

0

0

0

0

0

 

16

BEAM/SLAB NH SIDE

11

0

11

0

0

0

0

0

staging started

17

BEAM/SLAB RAILWAY SPAN

3

0

3

0

0

0

0

0

 

18

HR/FP/KERB CALICUT  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

19

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

20

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

21

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: Progress review done based on the revised Program (rev-01)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Availbility of Men

 

 

 

 

 

 

 

 

 

 

Date

21.02.11

22.02.11

23.02.11

24.02.11

25.02.11

 

 

 

 

 

No of labours

35

33

38

38

38

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

 

 

 

 

 

 

 

Material

Required

Available

Remarks

 

 

 

 

 

 

 

Coarse Aggreagate (m3)

40

150

 

 

 

 

 

 

 

 

Fine Aggreagate(m3)

24

85

materials are

 

 

 

 

 

 

 

Cement(bag)

340

1020

sufficient in site

 

 

 

 

 

 

 

Steel(MT)

10

195

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

 

 

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

 

 

 

 

 

 

BSNL

nil

 

 

 

 

 

 

 

 

 

KSEB

nil

 

 

 

 

 

 

 

 

 

KWA

nil

 

 

 

 

 

 

 

 

 

Others

nil

 

 

 

 

 

 

 

 

 

 
Back
 
    
AP1 PIERCAP CONCRETING (24.02.2011)

    
    
PIER AT NH SIDE NH (22.02.2011)

    
    
P2 TO P9 LOCATIONS (22.02.2011)

    
    
P18, P19, AP2 LOCATIONS(21.02.2011)

    
 
    
PEDESTAL CONCRETING IN P 17(21.02.2011)

    
    
PIER CONCRETING IN P5 TO P8 LOCATIONS (20.02.2011)

      
 

 

 

 

 

 

 

 