Shuttering work for girder between A1-P1
|
Shuttering work for girder-2 between A1-P1 |
Shuttering work for girder-2 between A1-P1
|
Shuttering work for girder-2 between A1- P1
|
Second girder concrete between A1- P1 |
Curing of girder.
|
Cable Profiling Work
|
Bottom shutter work girder-3 between A1-P1 |
Bottom shutter work girder-3 between A1-P1
|
Shuttering work for girder-1 between P6-P7
|
Reinforcement work for girder-2 between P6- P7 |
Shuttering works for first beam at Kuttipuram side.
|
|
shuttering work for girder-1 between P6 -P7 |
shuttering work for girder-1 between P6 -P7
|
Reinforcement work girder-2 between P6- P7
|
Shuttering work for girder-1 between P6- P7 |
Reinforcement work for second beam at Kuttipuram side
|
|
Reinforcement work for girder-2 between P6-P7 |
Reinforcement work for girder-2 between P6-P7 |
|
|
|
|
|
|
|
|
|