Weekly Progress Report - 03.08.2020 to 08.08.2020 |
03.08.2020 |
04.08.2020 |
05.08.2020 |
06.08.2020 |
07.08.2020 |
08.08.2020 |
Expansion joint Shuttering work at A2. |
Expansion joint Shuttering work progressing at A2. |
Expansion joint Shuttering work progressing at A2. |
Painting Work - 1 span |
Putty work at P10-P11 span. |
Compaction work in embankment area (Aroor side) |
Electrical pole fixing |
Painting work at P4, P6, P7 pier cap, P4 pier |
Painting work at P5 pier cap |
Metal Crash barrier work |
PCC work for Kerb stone fixing at P11 pier area. |
Putty work at crash barrier (Vyttila side)
|
Excavation for drainage near Pamba steel. |
Metal crash barrier work progressing at vyttila side |
Metal beam crash barrier work starts at aroor side. |
GSB Rolling and compaction |
|
Metal crash barrier work progressing at aroor side (Le meridian side).
|
Metal crash barrier work progressing at vyttila side |
Drainage Spout fixing - 5 nos |
|
Crash Barrier Chipping Work |
|
Painting Work |
|
PCC for drainage near Pamba steel |
|
Excavation Work |
|
|