Weekly Progress Report - 27.07.2020 to 01.08.2020 |
27.07.2020 |
28.07.2020 |
29.07.2020 |
30.07.2020 |
31.07.2020 |
01.08.2020 |
Elevator work at Llift L3.
|
Elevator work at Llift L3.
|
Tile flooring at 1st floor.
|
Tile flooring at 3rd floor HOD toilet.
|
Electrical work at 1st floor |
Tile flooring at 1st floor HOD toilet. |
Tile flooring at 1st floor.
|
Tile flooring at 1st floor.
|
Plumbing work at ducts
|
Tile flooring at 1st floor.
|
Tile flooring at 1st floor. |
Electrical work at 7th floor. |
|
|
Elevator work at Llift L3.
|
Plumbing work at 5th floor gents toilet.
|
Terrace floor preparation for waterproofing
|
Plumbing work at 7th floor gents toilet. |
|
|
|
|
|
|
|
|
|
|
|
|