   Weekly Progress Report - 27.07.2020 to 01.08.2020
    
Weekly Progress Report - 27.07.2020 to 01.08.2020
27.07.2020 28.07.2020 29.07.2020 30.07.2020 31.07.2020 01.08.2020
Form-work preparation/installation for slab at -2.70m level at Zone A. Form-work preparation/installation for slab at -2.70m level at Zone A. No Work due to Heavy Rain Form-work preparation/installation for slab at -2.70m level at Zone A. No Work at Site Form-work preparation/installation for slab at -2.70m level at Zone A.
Reinforcement installation for beams and slab at -2.70m level at Zone A. Reinforcement installation for beams and slab at -2.70m level, Zone A.  
Reinforcement installation for beams and slab at -2.70m level, Zone A.
 
Reinforcement installation for beams and slab at -2.70m level, Zone A.
Reinforcement Cutting and bending of reinforcement for the slab,beams and columns. Reinforcement Cutting and bending of reinforcement for the slab,beams and columns.   Reinforcement Cutting and bending of reinforcement for the slab,beams and columns.  
Cutting and bending of reinforcement for the slab,beams and columns.
  Block work for Plinth at Zone B.   Block work for Plinth at Zone B.  
Block work construction for Plinth walls at Zone B.
           



 

 
Back
 
    
BRICKWORK FOR PLINTH

    
    
REINFORCEMENT WORK

    
    
REINFORCEMENT BENDING WORK

    
    
REINFORCEMENT WORK

    
 
    
REINFORCEMENT WORK

    
    
FORMWORK INSTALLATION FOR SLAB

    
    
BLOCK WORK FOR PLINTH

    
 
    
REINFORCEMENT WORK

    
    
FORMWORK INSTALLATION

    
    
REINFORCEMENT BENDING WORK

    
 
 
 

 

 

 

 

 

 

 

Untitled Document