Weekly Progress Report - 27.07.2020 to 01.08.2020 |
27.07.2020 |
28.07.2020 |
29.07.2020 |
30.07.2020 |
31.07.2020 |
01.08.2020 |
Putty Work- P11-P12 span, P7-P8 span, P3 pier cap |
Putty Work - Half span |
Painting Work- 1 span |
Painting work progressing at P2-P3. |
Compaction work at embankment area (Aroor side) |
Compaction work at embankment area (Aroor side) |
Embankment Filling and Rolling |
Painting Work- 1 span and 1 pier cap |
Putty Work - Half span |
Primer coating progressing at P9-P10 |
Expansion joint work progressing at A2 (Aroor side). |
Painting - One pier cap and P7-P8 span |
Approach Road Widening in Aroor side |
Expansion Joint Installation |
|
Expansion Joint Installation at Aroor side |
PCC work for laying Kerb stone on Median side at Vyttila embankment area |
Electrical pole fixing at vyttila side - 5 nos |
|
|
|
Soil Filling at Pier bottom |
|
|
|
|
|
|
|
|