Weekly Progress Report - 20.07.2020 to 25.07.2020 |
20.07.2020 |
21.07.2020 |
22.07.2020 |
23.07.2020 |
24.07.2020 |
25.07.2020 |
Reinforcement works for Girder between P1-P2 |
Reinforcement works for Girder between P1-P2 |
Shuttering works for Girder between P1-P2 |
Shuttering works for Girder between P1-P2 |
Concreting for Girder between P1-P2 |
Reinforcement works for second Girder at first span of Thrissur side |
Reinforcement works at yard for Girder works at Kuttipuram side |
Reinforcement works at yard for Girder works at Kuttipuram side |
Reinforcement works at yard for Girder works at Kuttipuram side |
Reinforcement works for Girder works at Kuttipuram side |
Reinforcement works for Girder works at Kuttipuram side |
Reinforcement works for Girder works at Kuttipuram side |
|
|
|
|
|
De Shuttering for Girder between P1-P2 |
|
|
|
|
|
|
|
|
|
|
|
|