Weekly Progress Report - 20.07.2020 to 25.07.2020 |
20.07.2020 |
21.07.2020 |
22.07.2020 |
23.07.2020 |
24.07.2020 |
25.07.2020 |
Tile flooring at 3rd floor |
Sunken filling at 5th floor gents toilet |
Tile flooring at 3rd floor |
Tile flooring at 3rd floor |
Elevator work at Llift L3. |
Plastering work at lift opening |
Elevator work at Llift L1. |
Plumbing pipe laying at 7th floor gents toilet |
Plumbing pipe laying at duct |
Plumbing pipe laying at 7th floor. |
Plastering work at lift opening. |
Elevator work at Llift L3. |
Plumbing rain water pipe laying at terrace. |
Tile flooring at 3rd floor |
Elevator work at Llift L3. |
Elevator work at Llift L3. |
Tile flooring at 2nd floor |
Sunken filling at 4th floor gents toilet |
|
Elevator work at Llift L3.
|
|
|
|
Tile flooring at 2nd floor passage
|
|
|
|
|
|
|