Weekly Progress Report - 20.07.2020 to 25.07.2020 |
20.07.2020 |
21.07.2020 |
22.07.2020 |
23.07.2020 |
24.07.2020 |
25.07.2020 |
Putty Work- half span |
Putty Work- half span |
Putty Work- half span |
Putty work - half span. |
Putty work - half span. |
Putty work - half span. |
Painting work-1 Span |
Painting work-1 Span |
Painting work-1 Span |
Painting work-1 Span |
Painting work-1 Span |
Painting work-1 Span, 2 piercap and 2 piers |
Drainage spout fixing-13No |
WMM Compaction at Aroor side |
GSB filling -30m3 |
Reinforcement for approach slab at Aroor Side- 12 m |
Reinforcement for approach slab at Aroor Side - 24 m |
Approach Slab Concrete - 24 m (Including Reinforcement and Shuttering) |
Soil filling -60m3 |
Electric light post works progressing on bridge portion (lemeridian side full) |
Gabion work- 6 m3 |
Kerb stone - 60 m |
Kerb stone - 70 m |
Kerb stone laying around 4 piers |
|
Gabion work- 6 m3 |
Shuttering completed and PCC done for half portion at Aroor side approach portion |
Drainage spout - 13 nos |
Drainage spout - 12 nos |
Embankment Filling and Rolling - 20 m3 |