Prevoius Weekly Reports

   Weekly Progress Report 13.07.2020 - 18.07.2020
    
Weekly Progress Report - 13.07.2020 to 18.07.2020
13.07.2020 14.07.2020 15.07.2020 16.07.2020 17.07.2020 18.07.2020
Tile flooring at 1st floor ladies toilet Tile flooring at 1st floor ladies toilet Elevator work at Lift L3 Tile flooring at 1st floor ladies toilet Tile flooring at 3rd floor  Tile flooring at 3rd floor
Elevator work at Llift L3 Elevator work at Lift L3 1st floor duct plastering  Elevator work at Lift L3 Elevator work at Lift L3 Elevator work at Llift L3
    Plumping work in HOD duct area Plumbing work at Duct Plumbing work at Duct Plumbing work at 7th floor gents toilet
          Screeding concrete at lift machine room.
 
           
 
Back
 
    
SCREEDING AT LIFT MACHINE ROOM

    
    
TILE FLOORING

    
    
PLUMBING

    
    
LIFT L3

    
 
    
ELEVATOR WORK AT LIFT L3

    
    
ELEVATOR WORK AT LIFT L3

    
    
TILE FLOORING AT 1ST FLOOR LADIES TOILET

    
 
    
ELEVATOR WORK AT LIFT L3

    
    
ELEVATOR WORK AT LIFT L3

    
    
ELEVATOR WORK AT LLIFT L3

    
 
 
 

 

 

 

 

 

 

 