Weekly Progress Report - 13.07.2020 to 18.07.2020 |
13.07.2020 |
14.07.2020 |
15.07.2020 |
16.07.2020 |
17.07.2020 |
18.07.2020 |
Tile flooring at 1st floor ladies toilet |
Tile flooring at 1st floor ladies toilet |
Elevator work at Lift L3 |
Tile flooring at 1st floor ladies toilet |
Tile flooring at 3rd floor |
Tile flooring at 3rd floor |
Elevator work at Llift L3 |
Elevator work at Lift L3 |
1st floor duct plastering |
Elevator work at Lift L3 |
Elevator work at Lift L3 |
Elevator work at Llift L3 |
|
|
Plumping work in HOD duct area |
Plumbing work at Duct |
Plumbing work at Duct |
Plumbing work at 7th floor gents toilet |
|
|
|
|
|
Screeding concrete at lift machine room.
|
|
|
|
|
|
|