   Weekly Progress Report - 13.07.2020 to 18.07.2020
    
Weekly Progress Report - 13.07.2020 to 18.07.2020
13.07.2020 14.07.2020 15.07.2020 16.07.2020 17.07.2020 18.07.2020
No major works due to rain Conreting of girder between A1-P1 Deshuttering works at Girder between A1-P1. Deshuttering works of Girder Reinforcement works for Girder between P1-P2. Reinforcement works for Girder between P1-P2.
    Arrangement for Girder works at Kuttipuram side Reinforcement bending works in progress for Girder at Kuttipuram side    
           
           
           



 

 
Back
 
    
DESHUTTERING WORKS AT GIRDER BETWEEN A1-P1

    
    
CONRETING OF GIRDER

    
    
CONRETING OF GIRDER BETWEEN A1-P1

      
 

 

 

 

 

 

 

 