Prevoius Weekly Reports

   weekly progress 25.2.2011
    

 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

Remarks

1

Re wall towards NH side

100%

10

100

19

15

10

5

10

 

2

RE wall towards Pulikkakadavuside

100%

100%

0

39

1

1

0

0

 

3

Approach

 Span

5 No

4

1

28

-

-

-

-

 

4

Railway

 span

3No

0

0

26

 

 

 

 

 

5

Pile (Rly)pulikakadavuside

9

4

 

5

46

 0

0

0

 caution awaited.

6

Pile (Rly)Nhside

9

4

5

 

 

0

0

0

 shifting of railway signal cables isin progress

 6

Pile  cap

4No

0

4

36

 1

 0

 1

 1

 

Reinforcement and shuttering work for pile cap P2 completed.

7

 

Handrail

(in the pulikkakadavuside)

 

426m

420

6

 

 50

50

 -

 6

 

8

Kerb

639m

600

39

-

 70

 70

-

 39

 

 

Date 19.2.2011 21.2.2011 22.2.2011 23.2.2011 24.2.2011 25.2.2011
Labour 47 28 30 35 35 34 

 

Material Stocking Status

 

Required

Available

Remarks

Fine Aggreagate(m3)

 6.5

 12

 

Cement(bag)

 80

 34

 stock will replenished beforemonday

Steel(MT)

 4

 30

 

 Coarse Aggreagate(m3

 16

 20

 pile cap concrete will be  done using RMC  .

 

Utility shifting

 

 

Utilities to be shifted

Status

Action taken

BSNL

 nil

 

KSEB

 1 service line at the NH side to be removed.

 informedto  KSEB  authorities.

KWA

 serviceline at the approach portion of the NH side

 temporary shifting done.

Others

 railway signal cable and reliance cable at P7,P8

 cable shifting is in progress near P7

 

 
Back
 
    
CONCRETING OF PILE ON NH SIDE 19.2.2011

    
    
FIXING REINFORCEMENT FOR FOOTPATH SLAB

    
    
WORK OF HAND RAIL 21.2.2011

    
    
STAGGING ARRANGEMENT FOR SPAN P3P2.

    
 
    
SHIFTING OF RAILWAYS SIGNAL CABLE 25.2.2011

    
    
RE WALL WORK ON NH SIDE 25.2.2011

    
    
RE WALL WORK ON NH SIDE 19.2.2011

    
 
 
 

 

 

 

 

 

 

 