   Weekly Progress Report - 13.07.2020 to 18.07.2020
    
Weekly Progress Report - 13.07.2020 to 18.07.2020
13.07.2020 14.07.2020 15.07.2020 16.07.2020 17.07.2020 18.07.2020
Putty Work- 1 span Putty works -1 piercap Painting work-1 Span Painting work - 1 span Gabion work-4m3  Putty work - half span
Crash Barrier concreting-9.5m3 Painting work-1 Span Putty works -1 piercap Putty work - half span Putty work - half span Gabion work-5m3 
Drainage spout fixing-10No Gabion work-4m3            GSB filling works  Gabion work-4m3     No major works due to rain No major works due to rain Drainage spout fixing-13No
  Drainage spout fixing-10Nos Earth filling -35m3     GSB filling works -45m3
  Deshuttering work-26m        
 
Back
 
    
GABION WALL WORK

    
    
PAINTING

    
    
DRAINAGE SPOUT

    
    
GSB LEVELLING

    
 
    
PUTTY WORKS

    
    
GABION WALL WORK

    
    
PUTTY WORKS

    
 
    
PAINTING WORK

    
    
PUTTY WORK

    
    
GABION WALL WORK

    
 
    
PAINTING WORKS

    
    
PUTTY PATCH WORK

    
    
GSB LAYING WORK

    
 
    
PAINTING WORKS

    
    
PAINTING WORKS

    
    
GABION WALL WORK

    
 
    
DRAINAGE SPOUT FIXING

    
    
GSB FILLING

    
    
DESHUTTERING WORK

    
 
    
PUTTY WORK

    
    
CRASH BARRIER CONCRETING WORK

    
    
PUTTY WORKS

    
 
    
CRASH BARRIER WORKS

      
 

 

 

 

 

 

 

 