Weekly Progress Report - 06.07.2020 to 11.07.2020 |
06.07.2020 |
07.07.2020 |
08.07.2020 |
09.07.2020 |
10.07.2020 |
11.07.2020 |
Putty Work- 1 span |
Putty Work- 1 span |
primer coat works- half span |
Putty Work- 1 span |
Putty Work- 1 span |
Putty Work- 1 span |
primer coat works- 1 span |
primer coat works- halfspan |
Putty Work- 1 span |
Shuttering work for crash barrier-26m |
primer coat works- half span |
primer coat works- half span |
Shuttering work for crash barrier |
paver block laying works-288m2 |
paver block laying works-100m2 |
Gabion work-4m3 |
Gabion work-8m3 |
Shuttering work for crash barrier-26m |
paver block laying works |
|
Earth filling-45m3 |
crash barrier conreting-9.5m3 |
paver block laying works-50m2 |
Gabion work-5m3 |
Drain excavation |
|
shutter supporting-26m |
PCC work at paver block side-2.5m3 |
Deshuttering work for crash barrier |
Excavation-120m3
|