Weekly Progress Report - 29.06.2020 to 04.07.2020 |
29.06.2020 |
30.06.2020 |
01.07.2020 |
02.07.2020 |
03.07.2020 |
04.07.2020 |
Putty Work- 1 span |
Putty work in P2-P3,P4-P5 Crash barrier in vyttila side. |
Putty work - 1 span |
Putty work -1span |
Putty work -1span |
Primer coating- half span |
primer coat works-2415m2 |
Primer coat (painting) work at P2-P1 span. |
Primer coating - half span |
Primer coating- half span |
Primer coating- half span |
Paver block laying |
kerb stone fixing -20m |
Kerb stone fixing- 27.1m |
Paver block laying - 110sqm |
Paver block laying-300m2 |
Paver block laying-1 span |
Shuttering work for crash barrier |
paver block laying works |
Paver block rectification work |
Shuttering work for crash barrier haunch - 26 m |
Shuttering work for crash barrier haunch-26m |
Concreting work crash barrier hauch portion- 9 m3 |
Electrical work and cleaning work |
crash barrier concreting- 13m3 |
Site clearing work at P10-P11 |
Site cleaning work at P11-P12 |
Drain excavation at Thripunitura side-18x1.6x1.2 |
Electrical work and cleaning work |
Putty work & Kerb stone fixing |