Weekly Progress Report - 22.06.2020 to 27.06.2020 |
22.06.2020 |
23.06.2020 |
24.06.2020 |
25.06.2020 |
26.06.2020 |
27.06.2020 |
Elevator work at L1 machine room
|
Elevator work at L1 machine room |
Elevator work at L1 & L2 machine room |
Elevator work at L3 |
Elevator work at L3 |
1st floor duct block work |
Elevator work at L2.
|
Elevator work at L2 |
Plumbing pipe laying at 5th floor |
Plumbing rail fixing at duct |
Plumbing rail fixing at duct |
1st floor lintel shuttering and steel work |
LadiesToilet Wash basin slab shuttering and steel work. |
Plumbing pipe laying at 4th floor |
First floor duct shuttering work |
6th floor gents toilet lintel shuttering and steel work |
1st floor duct shuttering and steel work |
Plumbing rain water pipe fixing at west side |
|
First floor duct blockwork |
ELV works at 6th floor |
|
Duct block work at 1st floor |
|
|
|
Main stair granite flooring |
|
|
|