Weekly Progress Report - 22.06.2020 to 27.06.2020 |
22.06.2020 |
23.06.2020 |
24.06.2020 |
25.06.2020 |
26.06.2020 |
27.06.2020 |
Putty Work- 1 span |
Putty Work- 1 span |
Shuttering work for crash barrier haunch at Aroor side-15m |
Shuttering work for crash barrier - 18m |
Paver block laying (P9-P10)-360m2 |
Paver block laying (P9-P10)-150m2 |
Electric Bulb fixing |
Expansion Joint Installation |
Paver block laying (P8-P9)-100m2 |
Emulsion work- 7485m2 |
Kerb stone fixing- 51.9m |
Kerb stone fixing- 39m |
Expansion Joint Installation |
Paver Blocks laying- 1 span |
Kerb stone fixing (around P4)- 18.9m |
Paver block laying (P9-P10)-200m2 |
PCC work Kerb stone fixing-2m3 |
Putty work-1 span |
Site Cleaning |
Reinforcement work for crash barrier at Aroor side( Le Meridian side)-15 m |
Compaction works at Aroor Embankment and electrical works |
Kerb stone fixing- 37.2m |
Putty work-1 span |
|
|
Kerb placing, excavation work and electrical Connection works |
Expantion joint fixing work at A2 |
Putty work( Crash barrier inner side- 900m |
|
|