Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886258
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report 15.06.2020 - 20.06.2020
    
Weekly Progress Report - 15.06.2020 to 20.06.2020
15.06.2020 16.06.2020 17.06.2020 18.06.2020 19.06.2020 20.06.2020
Third floor cold room inside plastering Wash basin steel and shuttering work at 1st floor Ladies toilet

Wash basin slab shuttering work at 3rd floor Ladies toilet

Wash basin slab shuttering work at 3rd floor Ladies toilet

Duct block work at 1st floor a Grid A7 ELV Wire pulling at 4th floor
Elevator works at L1 & L2 Elevator works at L1 & L2 Elevator works at L1 & L2 Elevator works at L1 & L2 Fin wall primer coating Elevator works at L1,L2 &L3
Fire pipe installation works ELV Wire pulling at 5th floor ELV Wire pulling at 5th floor ELV Wire pulling at 4th floor First floor duct steel and shuttering work at Grid A4 OHT plastering
OHT external plastering Fire pressure test at 7th floor   Granite moulding at 5th floor ELV Wire pulling at 4th floor  
Plumbing works at ducts Plumbing work at Duct     Elevator works at L3  
 
Back
 
    
ELV WIRE PULLING AT 4TH FLOOR

    
    
LIFT L1

    
    
OHT PLASTERING

    
    
FIN WALL PRIMER APPLICATION

    
 
    
ELV WIRE PULLING AT 4TH FLOOR

    
    
DUCT STEEL AND SHUTTERING WORK

    
    
ELV WIRE PULLING AT 4TH FLOOR

    
 
    
GRANITE MOULDING

    
    
LIFT WORK L2

    
    
WASH BASIN SLAB SHUTTERING AND STEEL WORK

    
 
    
LIFT WORK L2

    
    
ELV WIRE PULLING

    
    
WASH BASIN SLAB SHUTTERING WORK AT 3RD FLOOR

    
 
    
SHUTTERING WORK OF WASH BASIN

    
    
PLUMBING WORK

    
    
LIFT WORK L2

    
 
    
LIFT WORK L1

    
    
PLASTERING WORK

    
    
OVER HEAD TANK PLASTERING

    
 
    
LIFT WORK AT L2

    
    
FIRE PIPE INSTALLATION WORK

      
 

 

 

 

 

 

 

 

Untitled Document