Weekly Progress Report - 15.06.2020 to 20.06.2020 |
15.06.2020 |
16.06.2020 |
17.06.2020 |
18.06.2020 |
19.06.2020 |
20.06.2020 |
Deshuttering of crash barrier at Vyttilla side |
Crash barrier shuttering work-32m |
Crash barrier shuttering work-32m |
Crash barrier concreting at Vyttilla side-12m3 |
Kerb stone fixing- 30m |
Crash barrier reinforcement work -15.5m |
Expantion joint installation work |
Site clearing work |
Site Cleaning for laying paver blocks- 1 span |
Paver block laying under (P7-P8)-288m2 |
Paver block laying under (P7-P8)-360m2 |
Paver block laying-100m2 |
Gabion wall works |
Putty work-1 span |
Putty work-1 span |
Kerb stone fixing -30m |
Deshuttering of Crash barrier |
Kerb stone fixing- 48.4m |
Aroor side earth compaction work |
|
|
Putty work-1 span |
Putty works-1 span |
Putty works-1 span |
Site clearing and putty works |
|
|
|
|
Electrical light fixing-20nos |