Weekly Progress Report - 15.06.2020 to 20.06.2020 |
15.06.2020 |
16.06.2020 |
17.06.2020 |
18.06.2020 |
19.06.2020 |
20.06.2020 |
Concrete Pouring for Columns at Zone A and Zone B |
Formwork preparation & installation for slab at -2.70m level, Zone A |
Formwork preparation/installation for slab at -2.70m level at Zone A |
Formwork preparation/installation for slab at -2.70m level at Zone A |
Formwork preparation/installation for slab at -2.70m level at Zone A |
Shuttering works for Columns at Zone A & Zone B |
Concrete Pouring for Stair at Zone A |
Reinforcement installation for Columns at Zone A |
Reinforcement installation for Columns at Zone A and Zone B |
Reinforcement installation for Columns at Zone B |
Reinforcement installation for Columns at Zone B |
Reinforcement installation for Columns at Zone A |
Concrete Pouring for Sill Level Slab at Zone B |
Cutting and Bending of Reinforcement for the slab,beams and columns |
Shuttering works for Columns at Zone A |
Shuttering works for Columns at Zone A |
Reinforcement cutting and bending for the slab,beams and columns |
Cutting and Bending of Reinforcement for the slab,beams and columns |
|
|
Reinforcement cutting and bending for the slab,beams and columns |
Reinforcement cutting and bending for the slab,beams and columns |
|
|
|
|
|
|
|
|