   Weekly Progress Report 15.06.2020 - 20.06.2020
    
Weekly Progress Report - 15.06.2020 to 20.06.2020
15.06.2020 16.06.2020 17.06.2020 18.06.2020 19.06.2020 20.06.2020
Concrete Pouring for Columns at Zone A and Zone B Formwork preparation & installation for slab at -2.70m level, Zone A Formwork preparation/installation for slab at -2.70m level at Zone A Formwork preparation/installation for slab at -2.70m level at Zone A Formwork preparation/installation for slab at -2.70m level at Zone A Shuttering works for Columns at Zone A & Zone B
Concrete Pouring for Stair at Zone A Reinforcement installation for Columns at Zone A Reinforcement installation for Columns at Zone A and Zone B Reinforcement installation for Columns at Zone B Reinforcement installation for Columns at Zone B Reinforcement installation for Columns at Zone A
Concrete Pouring for Sill Level Slab at Zone B Cutting and Bending of Reinforcement for the slab,beams and columns Shuttering works for Columns at Zone A Shuttering works for Columns at Zone A Reinforcement cutting and bending for the slab,beams and columns Cutting and Bending of Reinforcement for the slab,beams and columns
    Reinforcement cutting and bending for the slab,beams and columns Reinforcement cutting and bending for the slab,beams and columns    
           
 
Back
 
    
SHUTTERING OF COLUMNS

    
    
REINFORCEMENT WORK FOR COLUMNS

    
    
COLUMN SHUTTERING

    
    
COLUMN REINFORCEMENT WORK

    
 
    
FORMWORK INSTALLATION FOR SLAB AT -2.70M LEVEL AT ZONE A

    
    
REINFORCEMENT INSTALLATION FOR COLUMNS

    
    
RETAINING WALL

    
 
    
DESHUTTERING OF COLUMN

    
    
FORMWORK INSTALLATION FOR SLAB AT -2.70M LEVEL AT ZONE A

    
    
SHUTTERING OF COLUMN

    
 
    
STEEL WORK AT YARD

    
    
REINFORCEMENT WORK OF COLUMN

    
    
FORMWORK INSTALLATION FOR SLAB AT -2.70M LEVEL AT ZONE A

    
 
    
COLUMN SHUTTERING

    
    
STAIRCASE WORK

    
    
SHUTTERING OF COLUMN

    
 
    
RETAINING WALL

    
    
REINFORCEMENT WORK OF COLUMN

    
    
CONCRETE POURING FOR COLUMNS

    
 
    
CONCRETE POURING FOR SILL LEVEL SLAB AT ZONE B

    
    
CONCRETE POURING FOR STAIR AT ZONE A

      
 

 

 

 

 

 

 

 