Weekly Progress Report - 08.06.2020 to 13.06.2020 |
08.06.2020 |
09.06.2020 |
10.06.2020 |
11.06.2020 |
12.06.2020 |
13.06.2020 |
Gabion wall work -12 m3
|
Gabion wall work -10 m3 |
Gabion wall work -12 m3 |
Gabion wall work -9 m3 |
Putty work - P9 pier and A1-P0 span |
Gabion wall work -10.5 m3 |
Electric pole -5nos
|
Deshuttering At Vytila side retaining wall- 20 m |
De Shuttering for retaining wall on Le Meredian Side- 15 m |
Shuttering For Retaining wall (Crown plaza side) -11 m |
Site Cleaning- P9-P10 Span |
Putty work- 1 span |
Putty- 1 span
|
Shuttering for retaining wall at Le Meridian side (Aroor side)- 15 m
Formwork for retaining wall shuttering at Crowne Plaza side( Aroor side) - 11 m
|
Formwork and Shuttering for retaining wall shuttering at Crowne Plaza side( Aroor side) - 26 m
|
Crash barrier Shuttering(Vyttila embankment side) -37 m. |
No Major works due to heavy rain |
Crash barrier Shuttering(Vyttila embankment side) - 40m. |
Shuttering for retaining wall on Le Meredian Side- 15 m
|
Embankment Filling and Compaction (Aroor side)- 140 m3 |
Putty work- 1 span |
Putty work- 1 span |
|
Site Cleaning |
Earth filling and compaction on Aroor side embankment -120 m3
Bridge Deck Cleaning - 30m
Site Cleaning and earth removal
|
Removing Soil at new underpass- 140 m3,
Bridge deck cleaning- 30m
Putty work- 1 span
Site Cleaning at various spans
|
Bridge deck cleaning- 30m
Site Cleaning at various spans
|
Site Cleaning |
|
|