   Weekly Progress Report 08.06.2020 - 13.06.2020
    
Weekly Progress Report - 08.06.2020 to 13.06.2020
08.06.2020 09.06.2020 10.06.2020 11.06.2020 12.06.2020 13.06.2020
Formwork preparation/installation for slab at -2.70m level at Zone A Formwork preparation/installation for slab at -2.70m level at Zone A Formwork preparation/installation for the slab at -2.70m level, Zone A Formwork preparation/installation for slab at -2.70m level, Zone A Formwork preparation/installation for slab and beams at -2.70m level, Zone A Formwork preparation/installation for slab at -2.70m level at Zone A
Shuttering works for Columns at Zone A Reinforcement cutting and bending for the slab, beams and columns Reinforcement installation for Columns at Zone B Reinforcement installation for Columns at Zone B Reinforcement cutting and bending for the slab,beams and columns Reinforcement cutting and bending for the slab,beams and columns
Reinforcement installation for Columns at Zone B   Reinforcement cutting and bending for the slab, beams and columns Reinforcement cutting and bending for the slab, beams and columns Preparations for casting the sill level slab supporting the precast vertical louvers  
      Preparations for casting of sill level slab supporting the precast louvers    
           
 
Back
 
    
STAIRCASE SHUTTERING

    
    
SHUTTERING OF COLUMN

    
    
RETAINING WALL

    
    
FORMWORK INSTALLATION FOR SLAB AT -2.70M LEVEL AT ZONE A

    
 
    
COLUMN SHUTTERING

    
    
SHUTTERING OF STAIRCASE

    
    
SHUTTERING OF COLUMN

    
 
    
PREPARATIONS FOR CASTING THE SILL LEVEL SLAB

    
    
FORMWORK INSTALLATION FOR SLAB AND BEAMS AT -2.70M LEVEL, ZONE A

    
    
COLUMN SHUTTERING

    
 
    
SHUTTERING WORK FOR COLUMNS

    
    
REINFORCEMENT INSTALLATION FOR COLUMNS AT ZONE B

    
    
FORMWORK INSTALLATION FOR SLAB AT -2.70M LEVEL, ZONE A.

    
 
    
FORMWORK INSTALLATION FOR SLAB AT -2.70M LEVEL- ZONE A.

    
    
FORMWORK INSTALLATION FOR THE SLAB AT -2.70M LEVEL, ZONE A

    
    
INTERNATIONAL GUEST HOUSE

    
 
    
REINFORCEMENT WORK OF COLUMNS

    
    
RETAINING WALL

    
    
SHUTTERING OF COLUMNS AT ENGINEERING BLOCK

    
 
    
SHUTTERING WORK OF COLUMNS

    
    
SHUTTERING WORK OF COLUMNS

    
    
SHUTTERING OF COLUMN

    
 
    
SHUTTERING OF BEAM

    
    
REINFORCEMENT CUTTING & BENDING

    
    
FORMWORK PREPARATION & INSTALLATION FOR SLAB AT -2.70M LEVEL AT ZONE A

    
 
    
SHUTTERING OF STAIRCASE

    
    
SHUTTERING OF COLUMN

    
    
RETAINING WALL

    
 
    
REINFORCEMENT WORK OF COLUMNS

    
    
REINFORCEMENT CUTTING AND BENDING

    
    
FORMWORK INSTALLATION FOR SLAB AT -2.70M LEVEL AT ZONE A

    
 
 
 

 

 

 

 

 

 

 