Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886220
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report 08.06.2020 - 13.06.2020
    
Weekly Progress Report - 08.06.2020 to 13.06.2020
08.06.2020 09.06.2020 10.06.2020 11.06.2020 12.06.2020 13.06.2020
Wash basin Granite work Main stair Granite flooring Granite flooring at the main stair Granite flooring at the main stair Third floor cold room inside plastering Third floor cold room inside plastering
Elevator works at L1 & L2 Elevator works at the L1 & L2 machine room Elevator works at L1 & L2 Elevator works at L1 & L2 Elevator works at L1 & L2 Elevator works at L1 & L2
6th floor gents toilet sunken filling ELV wire pulling at 6th floor Fins plastering Tile flooring at 4th floor Tile flooring at 4th floor First floor duct steel and shuttering work
Terrace floor primer coating Fins plastering Installation of Fire sprinkler pipes at 1st & 3rd floor Ceiling painting at 7th floor Ceiling painting at 6th floor OHT external plastering
Lift machine room terrace water proofing Rain water pipe laying at terrace floor Plumbing work at the 7th floor gents toilet
 
Plumbing work at the 7th floor gents toilet
Fire pipe installation at 4th floor Plumbing works at ducts
 
Back
 
    
PLUMBING WORK

    
    
OVER HEAD TANK PLASTERING

    
    
LIFT WORK AT L1

    
    
DUCT STEEL AND SHUTTERING WORK

    
 
    
CEILING PAINTING

    
    
LIFT WORK (L2)

    
    
LIFT WORK L1

    
 
    
PLASTERING WORK

    
    
TILE WORK

    
    
CEILING PAINTING AT 7TH FLOOR

    
 
    
ELEVATOR WORK AT L2

    
    
TILE WORK AT 4TH FLOOR

    
    
GRANITE WORK

    
 
    
LIFT WORK

    
    
INSTALLATION OF FIRE SPRINKLER PIPE 3RD FLOOR

    
    
GRANITE LAYING WORK

    
 
    
INSTALLATION OF FIRE SPRINKLER PIPE 1ST FLOOR

    
    
LIFT WORK L2

    
    
FINS PLASTERING

    
 
    
GRANITE FLOORING

    
    
LIFT MACHINE ROOM L2 & L3

    
    
LIFT MACHINE ROOM L1

    
 
    
ELECTRICAL WORK

    
    
PLASTERING OF FINS

    
    
PLUMBING WORK

    
 
    
WATER PROOFING

    
    
PRIMER COATING

    
    
GRANITE WORK

    
 
    
FIRE PIPE INSTALLATION WORK

    
    
ELEVATOR WORK

      
 

 

 

 

 

 

 

 

Untitled Document