Weekly Progress Report - 01.06.2020 to 06.06.2020 |
01.06.2020 |
02.06.2020 |
03.06.2020 |
04.06.2020 |
05.06.2020 |
06.06.2020 |
3rd floor tile work |
3rd-floor tile work |
Elevator works at L1 & L2
|
Granite flooring at main stair.
|
Granite flooring at main stair |
Granite flooring at the main stair |
Electrical work at 3rd floor
|
Elevator works at L1 & L2
|
Waterproofing on fire stair headroom terrace and 1st floor ladies toilet
|
Elevator works at L1 & L2 |
Elevator works at L1 & L2 |
Installation of Fire sprinkler pipes at 7th floor |
Elevator works at L1 & L2 |
Installation of Fire sprinkler pipes at 2nd and 3rd floor |
Masonry work at 7th floor gents toilet.
|
Lift machine room terrace water proofing |
Fins plastering |
Electrical work at 3rd floor |
Installation of Fire sprinkler pipes |
1st floor plastering
|
Plumbing work at 6th floor gents toilet
|
Plumbing work at 5th floor gents toilet |
Electrical work at 3rd floor |
Concreting of overhead tank cover slab |
Fins plastering |
Electrical work at 1st floor
|
Installation of fire sprinkler pipes at 1st and 3rd floor
|
Electrical work at 3rd floor and fins plastering
|
Plumbing work at Duct |
Lift machine room terrace water proofing |