Weekly report - 01.06.2020 to 06.06.2020 |
01.06.2020 |
02.06.2020 |
03.06.2020 |
04.06.2020 |
05.06.2020 |
06.06.2020 |
Shuttering works at girder P1-P2 |
Cable profile checking of Girder between P1-P2 |
Shuttering works at girder P1-P2 |
Shuttering works at girder P1-P2 |
Support fixing and alignment of shutters for 2nd girder |
Girder concrete (1 No.) in P1-P2 span |
Bottom shuttering works for A1-P1 |
Arrangements for girder works at Kuttipuram side |
Bottom shuttering works for A1-P1 |
Bottom shuttering works for A1-P1 |
Arrangements for girder works at Kuttipuram side |
Arrangements for girder works at Kuttipuram side |
Arrangements for girder works at Kuttipuram side |
|
Arrangements for girder works at Kuttipuram side |
Arrangements for girder works at Kuttipuram side |
Moisture correction and sieve analysis for aggregates |
|