Weekly Progress Report - 01.06.2020 to 06.06.2020 |
01.06.2020 |
02.06.2020 |
03.06.2020 |
04.06.2020 |
05.06.2020 |
06.06.2020 |
Reinforcement Work for retaining wall (Aroor Side)- 15 m |
Gabion wall work at Aroor Side- 3 m3 |
Gabion wall work at Aroor Side- 9 m3 |
Gabion wall work at Aroor Side- 10.5 m3 |
Gabion wall work at Aroor Side- 9 m3 |
Gabion wall work at Aroor Side- 0.5 m3 |
Electrical Pole Fixing - 9 nos |
Electrical pole fixing- 5 nos |
Crash Barrier De-Shuttering Work on Vytila LHS side |
Crash Barrier Shuttering Work on Vytila RHS side- 25 m |
Crash barrier shuttering work on Vyttilla side- 24m |
Electric pole fixing- 7nos |
Earth Filling - 120 m3 |
PCC worke and concrete on sides of kerb - 2 m3 |
Crash Barrier Shuttering Work on Vytila RHS side- 20 m |
Putty work- 1 span |
Putty work- 1 span |
Crash barrier shuttering work on Vyttilla side- 42m |
Excavation at under passage- 63 m3 |
Putty work- 2 span |
WMM compaction work on embankment sides of Vyttila side. |
WMM compaction work on embankment sides of Vyttila side. |
Electric pole fixing- 5 nos |
Deck slab cleaning work -250m |
Putty work and WMM rolling work |
WMM compaction |
-Putty work- 1 span , -Drainage Work on Thripunithura side |
Electrical work |
WMM compaction work on embankment sides of Vyttila side. |
Putty work- 1 span |