Weekly Progress Report - 25.05.2020 to 30.05.2020 |
25.05.2020 |
26.05.2020 |
27.05.2020 |
28.05.2020 |
29.05.2020 |
30.05.2020 |
No work due to death of an employee |
Inter lock laying work (P6-P7) - 360 m2 |
Excavation for under pass at P12-P13 -400m3 |
Gabion work on Le meridian side-9m3 |
Gabion work on Le meridian side-13.5m3 |
Electric pole fixing - 5Nos |
|
Excavation for under pass at P12-P13 span -144 m3 |
Retaining wall shuttering &concreting crown plaza side- 8m3 |
PCC works at paver block edges- 1.5m3
WMM Laying at Vyttilla side-70m3
|
Crash barrier concreting work- 12.5m3 |
Gabion wall work at Aroor side-10m3 |
|
Putty work (girder outside portion)-P2-P3 Span |
Inter lock laying work-360m2 |
Filling and compaction work at Aroor side-15m3 |
Excavation work for underpass -100m3 |
Earth Filling at Aroor side -200m3 |
|
Earth filling at A2 approach road - 60 m3
|
Putty work -P1-P2,P3-P4 Span |
Retaining wall deshuttering on Aroor side and shuttering work of crash barrier |
Reinforcement work for crash barrier haunch- 15m |
Shuttering work for Crash barrier -20m |
|
|
Crash barrier shuttering on embankment of Vyttila side
Kerb works-62m(PCC-1m3)
|
Putty works -P4-P5 Span and P1, P2 pier |
Filling and compaction work -51m3
WMM laying work and putty works
|
WMM laying work and putty works |