Weekly Progress Report - 25.05.2020 to 30.05.2020 |
25.05.2020 |
26.05.2020 |
27.05.2020 |
28.05.2020 |
29.05.2020 |
30.05.2020 |
Girder concrete between P1-P2 |
Arrangement of shutters for other girders in P1-P2 |
Curing of girder |
cable profiling works of girder in P1-P2 |
cable profiling works of girder in P1-P2 |
cable profiling works of girder in P1-P2 |
|
Curing of girder |
Deshuttering of end cone |
Reinforcement works for girder in A1-P1 |
Bottom shuttering works for A1- P1 |
Shuttering works for A1- P1 girder |
|
|
Bottom shuttering works for Girder between A1- P1 |
|
Arrangements for Girder works at Kuttipuram side |
|
|
|
|
|
|
|
|
|
|
|
|
|