Weekly Progress Report - 25.05.2020 to 30.05.2020 |
25.05.2020 |
26.05.2020 |
27.05.2020 |
28.05.2020 |
29.05.2020 |
30.05.2020 |
External Fins steel and shuttering work |
Gents toilet block work |
4th floor ladies toilet tile work
|
4th & 7th floor tile work
|
4th floor tile work
|
Electrical work at 1st floor
|
Gents toilet inside block work at 7th floor |
Electrical wire pulling at 1st floor |
Gents toilet wall plastering at 1st floor
|
Electrical wire pulling at 1st floor |
Elevator works at L1 & L2 |
Elevator works at L1 & L2
|
Gents toilet inside plastering 1st floor |
Installation of Fire sprinkler pipes |
Electrical wire pulling at 1st floor
|
Elevator works at L1 & L2
|
Electrical work at 1st floor |
Plumbing work at duct
|
Electrical wire pulling at 1st floor |
4th floor ladies toilet tile work |
Installation of Fire sprinkler pipes
|
Plumbing work at 6th floor Gents toilet
|
Installation of Fire sprinkler pipes |
Installation of Fire sprinkler pipes
|
Elevator works |
Plumbing work at duct |
Elevator works
|
|
Lintel shuttering at steel work at 1st floor |
Block work at 1st floor
|