   Weekly report - 11.05.2020 to 16.05.2020
    
Weekly report - 11.05.2020 to 16.05.2020
11.05.2020 12.05.2020 13.05.2020 14.05.2020 15.05.2020 16.05.2020
Plastering external west side Tiling works in 5th, 6th and 7th floors

Installation of Fire sprinkler pipes

5th and 6th floor floor tiling work

6th floor Passage & 4th floor tiling work

6th floor Passage & 4th floor tiling work

Tiling works in 5th, 6th and 7th floors External Plastering Works

External Fins steel and shuttering work

Elevator work 

Stair head room external primer coating

Water proofing at OH water tank

Waste line and drinking water line pipe works completed from 7th to 2nd floor at ladies toilets Electrical & Plumbing Works Tiling work at 5th Installation of Fire sprinkler pipes

External Fins steel and shuttering work

Granite laying at  main stair

 
Back
 
    
WATER PROOFING AT OH WATER TANK

    
    
GRANITE LAYING AT MAIN STAIR

    
    
STAIR HEAD ROOM EXTERNAL PRIMER COATING

    
    
EXTERNAL FINS STEEL AND SHUTTERING WORK

    
 
    
6TH FLOOR PASSAGE TILING WORK

    
    
INSTALLATION OF FIRE SPRINKLER PIPES

    
    
INSTALLATION OF FIRE SPRINKLER PIPES

    
 
    
EXTERNAL FINS STEEL AND SHUTTERING WORK

    
    
FLOORING WORK

    
    
EXTERNAL PLASTERING

    
 
    

    
    

    
    

    
 
 
 

 

 

 

 

 

 

 