Weekly report - 11.05.2020 to 16.05.2020 |
11.05.2020 |
12.05.2020 |
13.05.2020 |
14.05.2020 |
15.05.2020 |
16.05.2020 |
Plastering external west side |
Tiling works in 5th, 6th and 7th floors |
Installation of Fire sprinkler pipes
|
5th and 6th floor floor tiling work
|
6th floor Passage & 4th floor tiling work
|
6th floor Passage & 4th floor tiling work
|
Tiling works in 5th, 6th and 7th floors |
External Plastering Works |
External Fins steel and shuttering work
|
Elevator work
|
Stair head room external primer coating
|
Water proofing at OH water tank
|
Waste line and drinking water line pipe works completed from 7th to 2nd floor at ladies toilets |
Electrical & Plumbing Works |
Tiling work at 5th & |
Installation of Fire sprinkler pipes |
External Fins steel and shuttering work
|
Granite laying at main stair
|