Weekly report - 11.05.2020 to 16.05.2020 |
11.05.2020 |
12.05.2020 |
13.05.2020 |
14.05.2020 |
15.05.2020 |
16.05.2020 |
Crash Barrier reinforcement work(A1 LHS & RHS Vyttilla) |
Crash Barrier reinforcement work(A1 LHS & RHS Vyttilla) |
Gabion wall rubble work -RHS and LHS Aroor |
Gabion wall rubble work -RHS and LHS Aroor |
Gabion wall rubble work - LHS Aroor |
Gabion wall rubble work - LHS Aroor |
GSB Laying -A1 Vyttilla side |
PCC Laying work -Vyttilla side Approach slab |
Interlock laying beneath P3-P4 |
Interlock laying beneath P3-P4 completed.Beneath P4-P5 is in progress |
Interlock laying beneath P4-P5 |
Interlock laying beneath P4-P5 |
Gabion wall rubble work -RHS and LHS Aroor side |
Gabion wall rubble work -RHS and LHS Aroor |
Red earth filling-A2 Aroor side |
Approach slab reinforcement work-Vyttilla side |
Approach slab reinforcement work-Vyttilla side |
Approach slab concreted |
Putty Work (P2-P3) |
Drain dismantling work-LHS Vyttillla side |
|
|
Eartfilling and compaction- A2 Side |
Eartfilling and compaction- A2 Side |
Interlock laying beneath P3-P4 |
Interlock laying beneath P3-P4 |
|
|
|
|