   Weekly report as on 25.02.2011
    

 

RBDCK Engineer-Radhakrishnan, Contact No.9447178783

KITCO Engineer - Santhosh.G, Contact No. 9447384217

GPT Engineer - Nikhil, Contact No. 9539007550 

 

Progress Report For Mulankunnathukavu ROB for the week ending on 25-02-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed  
2 PILE M.C SIDE 36 36 Completed  
3 PILE CAP SHORNUR SIDE 3 3 Completed  
4 PILE CAP  M.C SIDE 12 12 Completed  
5 PIER SHORNUR  SIDE 3 3 Completed  
6 PIER M.C SIDE 12 12 Completed  
7 PIER CAP SHORNUR  SIDE 3 3 Completed pedestal concreting
8 PIER CAP M.C SIDE 12 12 Completed *Pedastal concreting
9 RE/R WALL SHORNUR  SIDE 100% 0 100% 0 5.00% 4.00% 1.00% 15.00% earthwork excavation 
10 RE/R WALL M.C SIDE 100% 1 99% 0 5.00% 4.00% 1.00% 10.00% *  casting of panel
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0*  
12 BEAM/SLAB M.C SIDE 12 0 12 0 1 1 0 2 reinforcement and shuttering works of beam and deck slab for span P11-P12 is in progress.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 Utility shifting                 Completed
                     
                     
                     
  Availbility of Men                   
  Date 19.02.11 20.02.11 21.02.11 22.02.11 23.02.11 24.02.11 25.02.11    
  Nof labours 25 25 25 25 25 27 27    
                     
  Material Stocking Status                
    Required Available Remarks            
  Fine aggregate {m³} 60 40 stock wiill be replenished before next Monday    
  Cement(bag) 700 500 stock wiill be replenished before next Monday    
  Steel inT 12.35 25 sufficient material available at the site    
  Coarse Aggreagate (m3) 80 200              
  Utility shifting                  
  Utilities to be shifted   Remarks              
  BSNL no hindrance                
  KSEB already shifted                
  KWA no hindrance                
  Others road diversion to be start          

 

 

 
Back
 
    
REINFORCEMENT WORK FOR BEAM AND SLAB - 19.02.2011

    
    
SHUTTERING AND BARBENDING FOR BEAM AND SLAB - 21.02.2011

    
    
SHUTTERING WORK FOR BEAM - 22.02.2011

    
    
EARTH WORK FOR RE WALL AT SHORNUR SIDE - 23.02.2011

    
 
    
CONCRETING OF SIDE AP1 24.02.2011

    
    
SHUTTERING WORK FOR BEAM - 25.02.2011

      
 

 

 

 

 

 

 

 