Sl No. |
Item Description |
Status |
1 |
Retaining wall A2 Aroor LHS |
3rd lift completed |
2 |
Gabion Wall Rubble work LHS & RHS |
560cum completed |
3 |
Grinding and Putty work |
P2-P3, P3-P4, P9-P10 spans completed |
4 |
Crash Barrier Joint |
Reinforcement work in progress (sides of expansion joint) |
5 |
Expansion Joint |
P10 & P1 in finished |
6 |
Interlock Laying |
P1-P2, P2-P3 in completed |
7 |
Electrical Work |
Wiring is progressing |
|