Prevoius Weekly Reports

   04.05.2020 - 08.05.2020
    
Sl. No Activity Description Total Quantity Work  planned for last week   Actual work executed last week Total Quantity Executed till now Remarks
1 Platering West side (external) 873m2 200m2 110m2 721.1m2 North south and east external plastering completed
2 Flooring Work 2426.75m2 355m2 250m2 850m2  
3 Electrical Work          
  1st floor 100% 5% 0% 60%  
  2nd floor 100% 5% 0% 80%  
  3rd floor 100% 5% 0% 80%  
  4th floor 100% 5% 0% 80%  
  5th floor 100% 5% 0% 80%  
  6th floor 100% 5% 0% 80%  
  7th floor 100% 5% 0% 80%  
  lift machine rooms 100% 5% 0% 50%  
4 Plumbing Work          
  1st floor 100% 5% 5% 65%  
  2nd floor 100% 5% 5% 65%  
  3rd floor 100% 5% 5% 65%  
  4th floor 100% 5% 5% 65%  
  5th floor 100% 5% 5% 65%  
  6th floor 100% 10% 5% 65%  
  7th floor 100% 10% 5% 65%  
 
Back