Sl:No. |
Description of item |
Status |
|
1 |
Retaining wall A2 Aroor RHS |
wall 3rd lift -26.2 mts completed |
|
2 |
Gabion Wall Excavation |
481.5cum completed |
|
3 |
Gabion Wall Rubble work |
481.5cum completed |
|
4 |
Grinding and Putty work |
P1-P2, P7-P8,& P8-P9 spans completed |
|
5 |
Crash Barrier Joint |
Shuttering work and concreting work in progress |
|
6 |
Expansion Joint |
P10 & P1 in progress |
|
7 |
Interlock Laying |
P2-P3 in progress |
|